Today’s Date: Wednesday, June 26, 2013 at 9 am
District: 05 – Santa Barbara, San Luis Obispo, Monterey, San Benito and Santa
Cruz Counties
Contact: Susana Z Cruz (bilingual) or Colin Jones
Phone: (805) 549-3138 or 549-3189
FOR IMMEDIATE RELEASE

** UPDATE #37 **

HIGHWAY 1/ROCKY CREEK VIADUCT PROJECT CONTINUES WITH DAYTIME ROADWORK AND INTERMITTENT OVERNIGHT CLOSURES

Daytime roadwork on Highway 1 at Rocky Creek continues next week from 7 am to 5 pm Monday, July 1 and Tuesday, July 2. On Wednesday, July 3, roadwork will occur from 7 am to 12 noon. Up to 10-minute traffic delays are expected. There will no daytime roadwork as of noon next Wednesday, July 3, on Thursday, July 4 or Friday, July 5 due to the holiday.

NOTE: There will be NO OVERNIGHT FULL closures or NIGHT ROADWORK next week. .

The closures/delays are needed to construct a soldier pile wall.

NOTE: Through traffic has been shifted to the newly constructed southbound half of the viaduct while work continues on the northbound half.

The project to construct a permanent viaduct about 15 miles south of Carmel near the Rocky Creek Bridge began on Sept. 4, 2012. Completion is scheduled by the end of October, weather permitting. Daily roadwork schedules are subject to change due to weather conditions and other factors so stay tuned for regular updates.

The contractor for this $11 million viaduct project is Golden State Bridge of Martinez, CA.

Caltrans reminds motorists to move over and slow down when driving through highway work zones.

For more information, please visit: http://www.dot.ca.gov/dist05/paffairs/ or contact the Hwy. 1 Cambria to Carmel Toll-Free Hotline at 888-836-0866.

Susana Z. Cruz
Public Information Officer/
Portavoz de Relaciones Públicas
805. 549.3138
805.549.3326–fax

Advertisements

Read Full Post »

Today’s Date: Wednesday, June 19, 2013 at 9 am
District: 05 – Santa Barbara, San Luis Obispo, Monterey, San Benito and Santa
Cruz Counties
Contact: Susana Z Cruz (bilingual) or Colin Jones
Phone: (805) 549-3138 or 549-3189
FOR IMMEDIATE RELEASE

** UPDATE #36 **

HIGHWAY 1/ROCKY CREEK VIADUCT PROJECT CONTINUES WITH DAYTIME ROADWORK AND INTERMITTENT OVERNIGHT CLOSURES

Daytime roadwork on Highway 1 at Rocky Creek continues next week from 7 am to 5 pm Monday, June 24 through Friday, June 28 with 10-minute delays as needed.

NOTE: There be NO OVERNIGHT FULL closures next week, but there WILL be NIGHT ROADWORK and traffic may be held for up to 10-minutes as needed from 9 pm to 7 am, starting Sunday, June 23 through Thursday, June 27 (Friday at 7am). No overnight closures will occur on Friday/Saturday nights.

The closures/delays are needed to construct a soldier pile wall.

NOTE: Through traffic has been shifted to the newly constructed southbound half of the viaduct while work continues on the northbound half.

The project to construct a permanent viaduct about 15 miles south of Carmel near the Rocky Creek Bridge began on Sept. 4. Completion is scheduled for the end of October, weather permitting. Daily roadwork schedules are subject to change due to weather conditions and other factors so stay tuned for regular updates.

The contractor for this $11 million viaduct project is Golden State Bridge of Martinez, CA.

Caltrans reminds motorists to move over and slow down when driving through highway work zones.

For more information, please visit: http://www.dot.ca.gov/dist05/paffairs/ or contact the Hwy. 1 Cambria to Carmel Toll-Free Hotline at 888-836-0866.

Susana Z. Cruz
Public Information Officer/
Portavoz de Relaciones Públicas
805. 549.3138
805.549.3326–fax

Read Full Post »

Today’s Date: Wednesday, June 12, 2013 at 1 pm
District: 05 – Santa Barbara, San Luis Obispo, Monterey, San Benito and Santa
Cruz Counties
Contact: Susana Z Cruz (bilingual) or Colin Jones
Phone: (805) 549-3138 or 549-3189
FOR IMMEDIATE RELEASE

** UPDATE #35 **

HIGHWAY 1/ROCKY CREEK VIADUCT PROJECT CONTINUES WITH DAYTIME ROADWORK AND INTERMITTENT OVERNIGHT CLOSURES

Daytime roadwork on Highway 1 at Rocky Creek continues next week from 7 am to 5 pm Monday, June 17 through Friday, June 21 with 10-minute delays as needed.

NOTE: There be NO OVERNIGHT FULL closures next week, but there WILL be NIGHT ROADWORK and traffic may be held for up to 10-minutes as needed from 9 pm to 7 am, starting Sunday, June 16 through Thursday, June 20 (Friday at 7am). No overnight closures will occur on Friday/Saturday nights.

The closures/delays are needed to construct a soldier pile wall.

NOTE: Through traffic has been shifted to the newly constructed southbound half of the viaduct while work continues on the northbound half.

The project to construct a permanent viaduct about 15 miles south of Carmel near the Rocky Creek Bridge began on Sept. 4. Completion is scheduled for the end of October, weather permitting. Daily roadwork schedules are subject to change due to weather conditions and other factors so stay tuned for regular updates.

The contractor for this $11 million viaduct project is Golden State Bridge of Martinez, CA.

Caltrans reminds motorists to move over and slow down when driving through highway work zones.

For more information, please visit: http://www.dot.ca.gov/dist05/paffairs/ or contact the Hwy. 1 Cambria to Carmel Toll-Free Hotline at 888-836-0866.
# # #

Susana Z. Cruz
Public Information Officer/
Portavoz de Relaciones Públicas
805. 549.3138
805.549.3326–fax

Read Full Post »

Today’s Date: Wednesday, June 5, 2013 at 9 am
District: 05 – Santa Barbara, San Luis Obispo, Monterey, San Benito and Santa
Cruz Counties
Contact: Susana Z Cruz (bilingual) or Colin Jones
Phone: (805) 549-3138 or 549-3189
FOR IMMEDIATE RELEASE

** UPDATE #34 **

HIGHWAY 1/ROCKY CREEK VIADUCT PROJECT CONTINUES WITH DAYTIME ROADWORK AND INTERMITTENT OVERNIGHT CLOSURES

Daytime roadwork on Highway 1 at Rocky Creek continues next week from 7 am to 5 pm Monday, June 10 through Friday, June 14 with 10-minute delays as needed.

NOTE: There be NO OVERNIGHT FULL closures next week, but there WILL be NIGHT ROADWORK and traffic may be held for up to 10-minutes as needed from 9 pm to 7 am, starting Sunday, June 9 through Thursday, June 13 (Friday at 7am). No overnight closures will occur on Friday/Saturday nights.

The closures/delays are needed to construct a soldier pile wall.

NOTE: Through traffic has been shifted to the newly constructed southbound half of the viaduct while work commences on the northbound half.

The project to construct a permanent viaduct about 15 miles south of Carmel near the Rocky Creek Bridge began on Sept. 4. Completion is scheduled for the end of October, weather permitting. Daily roadwork schedules are subject to change due to weather conditions and other factors so stay tuned for regular updates.

The contractor for this $11 million viaduct project is Golden State Bridge of Martinez, CA.

Caltrans reminds motorists to move over and slow down when driving through highway work zones.

For more information, please visit: http://www.dot.ca.gov/dist05/paffairs/ or contact the Hwy. 1 Cambria to Carmel Toll-Free Hotline at 888-836-0866.
Susana Z. Cruz
Public Information Officer/
Portavoz de Relaciones Públicas
805. 549.3138
805.549.3326–fax